15 May 2015: Activities on Site

Tilbury Green Power (TGP) would like to bring you up to date with what’s been happening on its site in Tilbury Docks.

We have recently begun a ground survey. This is part of the preliminary work necessary before construction of the generating station gets underway. TGP’s contractors are using mobile equipment to check on ground conditions. The work is likely to continue during June and July.

Later in May, TGP will start to remove some concrete structures which lie just below the surface of the ground.
These are part of the old factory foundations. The work will involve digging them up and crushing the concrete. The crushed concrete will be re-used on site and the work will continue during June and July.

After that, probably starting in July, TGP will start to construct the new foundations for the generating station.

We will post more updates on the construction of the generating station as work progresses.